Office relocation IT planning is where abstract technology decisions become very physical. Cables in walls, internet circuits at the curb, equipment in racks, devices at desks. The relocations that go well were planned six months ahead; the ones that go badly were treated as a moving company problem until two weeks before move-in. Here's a practical timeline for IT planning during office relocation.
The 6-Month Timeline
An office relocation IT project for a small to mid-market business typically runs 4-6 months from kickoff to move-in day. The major phases:
- Months 6-5 — site selection input, lease negotiation IT contingencies, initial site survey of candidate spaces
- Months 5-4 — design phase: cabling layout, network architecture, ISP selection
- Months 4-3 — vendor procurement: ISP circuit orders (long lead time), cabling contractor, equipment procurement
- Months 3-2 — buildout: cabling installation, equipment delivery, configuration
- Months 2-1 — testing: connectivity validation, security configuration, application access verification
- Final weeks — staging move, user device staging, move-day execution
- Post-move — stabilization, troubleshooting, decommission of old space
Compressing this timeline introduces risk. The internet circuit alone often takes 60-90 days from order to install — if you wait until two months before move-in to order, you're moving into a building without internet.
The Site Selection Considerations
IT should have input during space selection:
- Carrier availability — which ISPs serve the building, what speeds, what timelines for new service
- Existing infrastructure — is there cabling already in place, is it usable
- Telecom room / MPOE location — is there proper space for network equipment
- Power and cooling — adequate electrical capacity, HVAC for IT equipment heat
- Cellular reception — many newer buildings have poor cellular; affects mobile work and failover
- Wi-Fi obstacles — building materials (concrete, steel, glass) affect coverage design
- Physical security — door access, surveillance options, separation of public and operational areas
- Floor layout — open vs. private offices affects cabling, conference room counts affect AV needs
The Cabling Decision
Structured cabling is a long-term decision. The right standards:
- Cat 6A as the baseline — supports 10GbE for 100m, future-proof through next equipment generation
- Fiber for inter-floor or longer runs — and for backbone connecting telecom rooms
- Two drops per workstation minimum — one for desktop/laptop, one for phone or future device
- Generous capacity in conference rooms — displays, video gear, occasional wired connections
- Wi-Fi access point drops planned — proper coverage requires more APs than typical office expects
- Labeling discipline — every cable identified on both ends with consistent scheme
- Documentation — patch panel mapping, cable runs, labeled drops
Cabling is one of the few IT investments that lasts 10-15 years. Overbuilding the cabling is much cheaper than retrofitting later.
The ISP Circuit Strategy
Internet circuit decisions for the new space:
- Primary fiber circuit — typically symmetric, sized for projected concurrent users + headroom
- Secondary diverse circuit — different carrier, different physical path entering the building
- Cellular failover — for resilience or for use during build-out before fiber is active
- Order timing — fiber installs typically 60-90 days; order early
- Suite/floor-level demarcation — confirm where the carrier brings service ends up
- Cross-connect coordination — if building has shared MPOE, coordinate with property management
Move-Day Execution
The actual move sequence:
- Old space equipment shut down on Friday after business hours
- Critical systems already replicated/staged at new space
- User devices transported (or freshly imaged at new space)
- Saturday: equipment installed at new space, network verified
- Sunday: application testing, user-by-user setup if needed
- Monday morning: floor support for first-day issues
- Old space wound down per lease terms
Have substantial IT presence on move weekend and the first week. Issues that surface in the first hours of business at the new space need immediate response.
The Post-Move Stabilization
Even with good planning, the first weeks at a new space surface issues — Wi-Fi dead spots, jacks not working, application access problems, printer connectivity. Plan for a 2-4 week stabilization period with active triage. After that, the new space should be stable for years.
If you're planning an office relocation, a free 30-minute conversation can help frame the IT planning timeline against your move date.
Leonidas is a managed IT services provider, cybersecurity consulting firm, and unified communications consultancy serving businesses across industries. We offer free 30-minute assessments. Contact us or call 850-614-9343.